pSHIELD - WP phone leaders 9. december 2010

Agenda: 1. An agreement for the delay that we will request. 5 min

  • delay for 3 months
  • every one agrees, SESM agrees depending

2. Date for the mid-term review  5 min

  • first week in February
  • only WP leaders of deliverables which are due to delivery, means: Thyia, SESM, and WP2 leader
  • others might join, but only on special invitation

3. Current status on the work for WP1 - WP7. Reporting by PM/TM, and WP Leaders

- WP1: THYIA & SESM 5 min

- WP2: THYIA 10 min

- WP3: ETH/SESM 10 min, ETH will be represented by SESM

- WP4: SCOM 10 min

- WP5: ED 10 min

- WP6: HAI 10 min

- WP7: CWIN 10 min

  • dissemination and exploitation plan

4. Other issues ?

  • Antonio Vecchio is project officer for nSHIELD
  • nSHIELD can start in May, if every country agrees - more probable start in September/October
  • overlap with pSHIELD is okay to get people in place

Technical Manager

  • Antonio di Marco - Technical manager: change technical manager from Elsag Datamag to SESM

Funding from JU

  • currently two signatures in place, Norway and Slovenia. Need a third signature, such that project is in place (Spain?)?
  • Form beneficiary…. (check mail, signature from all partners)
  • Mushfiq - transfer document structure to new BSCW -> Spase